Timeline For Kennewick High School Remodel Project

  • February - March 2017: Architect selected
  • Spring 2017: Architect conducts educational specifications process with staff 
  • Spring - Fall 2017: Community input meetings
  • May 2017 - May 2018: Building designed by architect
  • September - October 2018: Project cost estimates completed
  • November 2018: School Board passes bond resolution
  • February 2019: Bond election
  • April 2019: Construction begins 

MAIN PHONE NUMBER

(509) 222-7024

DEPARTMENT CONTACTS

Doug Carl
Director of Capital Projects
(509) 222-7024
Email
Ryan Jones
Project Coordinator
(509) 222-6810
Email
Dustin Fisk
Administrative Assistant
(509) 222-7024
Email

DOCUMENTS

GOALS FOR NEW PROJECTS

- Energy Efficiency

- Environmental Quality

- Safety

- Health and Comfort

- Durability/Maintainability

- Minimize Environmental Impact

By addressing the above goals with each school, the Kennewick School District will create effective well-designed facilities that can truly enhance student learning and improve academic performance while taking pride in the environmental impact we leave behind.