Kennewick High School

Project Details View all Projects

Start of Construction: June 2019

Opens: August 2021

Location: Existing campus at 500 S. Dayton St. (Map)

Square Feet: 292,600

Details: The new two-story school will replace the existing Kennewick High, which opened in 1951. It will include a science wing, a dining commons, a courtyard and other features, and will connect to the existing Lion's Den gym and remodeled auditorium.

Funding: Local bond dollars

Estimated Cost: $112 million